Decision Maker: Strategic Director of Housing
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Contract Award Approval
That:
1. The re-procurement strategy outlined in this report for a single stage tender through the Notting Hill Genesis (NHG) framework – for Construction Works and Associated Services, for the redevelopment of the Wickway Community Centre for an anticipated period of 110 weeks commencing on 24 February 2023, at an estimated contract value of £33,880,000 be approved by the Strategic Director of Housing and Modernisation, in consultation with the Cabinet Member for Council Homes and Homelessness.
2. The procurement strategy noted in paragraph 1 replacing the original procurement strategy approved by cabinet on 04 July 2021following the termination of that procurement process as further detailed in paragraphs 9-12 be noted by the Strategic Director of Housing and Modernisation, in consultation with the Cabinet Member for Council Homes and Homelessness.
3. The original procurement route selected under the under the Crown Commercial Services (CCS) framework was terminated for the reasons outlined in paragraph 9 be noted by the Strategic Director of Housing and Modernisation, in consultation with the Cabinet Member for Council Homes and Homelessness.
Publication date: 21/09/2022
Date of decision: 15/09/2022
Effective from: 29/09/2022
Accompanying Documents: