Decision details

Feasibility Grant Funding Approval (Elim Sites)

Decision Maker: Strategic Director of Housing

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To agree to funding through a grant agreement up to planning submission (Elim Sites)

Decision:

 

 

1.  That the project grant agreement for the Elim Site in Appendix 1 for Leathermarket CBS to deliver around 31 council homes, 3 homes for private sale and a community hub be approved.

 

2.  That it be noted that the inception / feasibility report milestone required to satisfy the feasibility stage and planning application stage was presented to the programme delivery board on 10 March 2020 and amended as directed by the board.

 

3.   That it be approved that up to £985,028 to be drawn down to complete the planning application stage in line with the project grant agreement.

Publication date: 23/06/2020

Date of decision: 23/06/2020

Effective from: 01/07/2020