Gateway 3 - Variation Decision Approval - Design services for proposed new office development (Queens Road 4)

Decision Maker: Strategic Director of Finance and Governance

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve variation to the scope of the design and professional services up to RIBA Stage 4

Decision:

1.  That the prior approval for the variation of the contract with Faithful & Gould for professional services for £232,636 for a period of 17 months from August 2018 plus a contingency sum of £80,000 as set out in paragraph 16 of the report to cover the project design stages 2 to 4 to enable the completion of the design phase be confirmed.

 

2.  That the prior approval for the variation of the contract with Wernick Buildings Limited for the specialist modular design services for £1,276,996 for a period of 17 months from August 2018 to cover the project design stages 2 to 4 to enable the completion of the design phase be confirmed.

 

Publication date: 01/04/2020

Date of decision: 30/03/2020

Effective from: 09/04/2020