Decision details

The Way Forward: Ledbury Estate high rise blocks

Decision Maker: Cabinet

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To note the result of the options appraisal for Ledbury Estate and approve a recommendation on future action

Decisions:

RESOLVED:

 

1.  That the results of the options appraisal carried out for the Ledbury Estate high rise blocks be noted.

 

2.  That it be agreed that the four high rise blocks should be refurbished and that land immediately adjacent to those blocks be used to build new homes (option B in paragraph 26 of the report) in accordance with the council plan which guarantees development on council housing land have at least 50% council rented homes and ensure a right to return for council tenants and leaseholders so local people can stay in the borough they call home.

 

3.  That the proposal to carry out the refurbishment of Bromyard proceed using the existing partnering contract and delegated approval process with Engie be noted and that the rest of the project proceed using existing frameworks or the partnering contract, the new contractor framework if in place, or a traditional procurement route, all activities to be run concurrently to ensure all homes can be provided as soon as possible.

 

4.  That the decision not to charge leaseholders in the four tower blocks for their element of the cost of the refurbishment works be approved.

 

5.  That the decision not to charge residents for the costs of the temporary heating and hot water communal systems to the four tower block residents be approved.

Report author: Michael Scorer

Publication date: 31/10/2018

Date of decision: 30/10/2018

Decided at meeting: 30/10/2018 - Cabinet

Effective from: 08/11/2018

Accompanying Documents: