Decision Maker: Strategic Director of Housing
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Contract award to contractors to build new housing units
1. That the award of a works contract for Tenda Road to Collier Contracts Limited in the sum of £1,943,027.57 and an additional contingency amount for £200,611.36 for a period of 52 weeks from the 30 July 2018 plus 12 weeks for mobilisation be approved.
2. That the total scheme costs of £2,482,847 as detailed in paragraphs 59-61 of the report be noted.
Publication date: 20/03/2018
Date of decision: 20/03/2018
Effective from: 28/03/2018
Accompanying Documents: