Decision Maker: Strategic Director of Housing
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Contract award to contractors to build 22 new housing units, a commercial unit, and a TRA meeting room.
1. That the award of a works contract for Ivy Church Lane, to Aspen Build (East Anglia) Limited for a contract sum of £5,555,148 and an additional contingency amount of £277,757 for a period of 82 weeks from site possession commencing 2 July 2018 plus 12 weeks mobilisation be approved.
2. That the project’s associated on costs of £1,115,560 as detailed in paragraph 60 of the report be noted.
Publication date: 20/03/2018
Date of decision: 20/03/2018