Decision details

Gateway 2 - Major works contractor framework (Lot 1) Fenner Close QHIP 2017-18 Works

Decision Maker: Strategic Director of Housing

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Contract award approval – Fenner Close QHIP

Decision:

That the award of the Fenner Close refurb QHIP 2017-18 works via a mini-competition from the major works constructor framework to Standage & Co. Ltd for a period of 24 working weeks, be approved.

Publication date: 02/02/2018

Date of decision: 31/01/2018

Effective from: 10/02/2018

Accompanying Documents: