Decision Maker: Strategic Director of Housing
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: Yes
Contract award to contractors to build 17 new housing units
1. That the award of works contract for 95a Meeting House Lane to ENGIE Regeneration Ltd in the sum of £7,296,533, commencing Monday 22 January 2018 for a period of 82 weeks from site possession be approved, and that the contractor’s change of name as set out in paragraph 9 of this report be noted.
2. That the total scheme costs of £8,552,680 noted in paragraph 61 of the report be noted.
Publication date: 21/12/2017
Date of decision: 21/12/2017
Effective from: 06/01/2018
Accompanying Documents: