Decision Maker: Chief Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To approve an award of contract for new facilities including playroom, changing rooms and play area in Peckham Rye Park and Common
That the award of the design and build contract for Revitalise Peckham Rye to Neilcott Construction Ltd for £2,897,794, and a contingency amount as detailed in the closed report, for the main works over a contract period of 46 calendar weeks commencing in May 2017 and completing in March 2018, be approved.
Publication date: 10/05/2017
Date of decision: 10/05/2017
Effective from: 18/05/2017
Accompanying Documents: