Decision Maker: Cabinet
Decision status: Information Only
Is Key decision?: Yes
Is subject to call in?: Yes
GLA procurement approval for Abbeyfield Estate HINE
RESOLVED:
1. That the revised procurement strategy for the use of the GLA’s London Development Panel framework to procure development partners for the Abbeyfield Estate High Investment Needs Estate (HINE) (Maydew House) works at an estimated value of £22m for an estimated period of 208 weeks from 21 August 2017 be approved.
2. That estimated internal fees of £651,200 and external fees of £1,577,000 making a total estimated scheme cost of £24,228,200 be noted.
Report author: Gerri Scott
Publication date: 14/12/2016
Date of decision: 13/12/2016
Decided at meeting: 13/12/2016 - Cabinet
Effective from: 22/12/2016