Decision Maker: Strategic Director of Children and Adult Services
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To approve the award of contract to appoint design team and professional consultants for SILS, 3 PRU and Day 6 facility
1. That the award of a professional service contract for the full design and project management services to develop a scheme to provide new accommodation for the Southwark Inclusive Learning Services 3 (SILS 3) Pupil Referral Unit (PRU) to Faithful and Gould, under the Scape framework be approved.
2. That the appointment will be a NEC3 professional services contract for approximately 148 weeks commencing 16 December 2016 for a fixed fee of £934,908.
Publication date: 04/11/2016
Date of decision: 04/11/2016
Effective from: 12/11/2016