Gateway 2 - Contract award: Approval direct housing delivery – Proposed new build general needs housing at Long Lane, SE1 – Appointment of contractor for main construction works

Decision Maker: Chief Executive

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the appointment of a building contractor for main construction works

Decision:

1.  That the award of the main works contract for the general needs housing at 169 Long Lane, SE1 to Morgan Sindall plc, in the sum of £4,685,850.40 for a contract period of 64 calendar weeks commencing 5 January 2015 be approved.

 

2.  That the need for sub-structure works to be undertaken in advance of the main works contract for the reasons given in paragraphs 10 -12 of the report be noted.

 

3.  That the previously agreed award of the sub-structure works contract for the general needs housing at 169 Long, Lane SE1 to Morgan Sindall plc, in the sum of £310,550.60 for a contract period of 5 calendar weeks commencing on 21 November 2014 be approved.

Publication date: 11/12/2014

Date of decision: 10/12/2014

Effective from: 19/12/2014

Accompanying Documents: