Decision details

Gateway 1: Major Works Contractor Framework

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Approval of the procurement prodcess for major works contractor framework

Decisions:

RESOLVED:

 

That the procurement strategy outlined in the report for a housing and related services major works contractor framework covering 4 lots (for main building works, district heating works and communal electrics work as further detailed in paragraph 9 of the report at a total estimated annual cost of up to £92m for a period of four (4) years from 1 September 2014, making a total estimated contract value of up to £368m be approved.

Report author: Gerri Scott

Publication date: 24/10/2013

Date of decision: 22/10/2013

Decided at meeting: 22/10/2013 - Cabinet

Effective from: 01/11/2013