Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
RESOLVED:
1. That the procurement strategy outlined in the report for the supply of gas to all sites consuming over 25,000 therms at an estimated value outlined in the closed version of the report be approved.
2. That the use of a Consortium contract to award the supply of gas to all sites consuming over 25,000 therms for a four year period from October 2012 be approved.
3. That the evaluation of the two buying consortia for the award of the contract proposed in the report, namely LASER and Buying Solutions be approved.
Publication date: 22/06/2011
Date of decision: 21/06/2011
Decided at meeting: 21/06/2011 - Cabinet
Effective from: 01/07/2011
Accompanying Documents: