Appropriation of Council owned land to planning purposes: 57-76 Northchurch (including ramp) with respect to the detailed consent for Aylesbury Plot 18; and Package B site (subplots 5 and 6,part), with respect to the detailed consent for First Development Site (FDS)
RESOLVED:
1. That the current position in relation to the delivery of the First Development Site (FDS) (Phase 1b/1c in the Aylesbury Area Action Plan (AAAP) of the Aylesbury regeneration programme be noted.
3. That the area of council-owned land hatched black on the plan at Appendix 1 of the report, identified as the FDS Package B site area, be confirmed as no longer required for the purposes for which it is currently held and it be resolved to appropriate the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972 (as amended).
4. That following completion of the appropriation at paragraph 3 above, the area of council-owned land hatched black on the plan at Appendix 1 of the report identified as the FDS Package B site area be confirmed as no longer required for planning purposes and it be resolved to appropriate the land to housing purposes in accordance with section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972 (as amended).
5. That it be noted that the intention would be to proceed on 2-step appropriation of the land hatched black on the plan at Appendix 1 of the report; this to take into account that Ellison House is currently still occupied until the forecast date of March 2021.
6. That the area of council-owned land hatched black on the plan at Appendix 2 of the report, identified as 57-76 Northchurch and Taplow ramp site area, be confirmed as no longer required for the purposes for which it is currently held and (upon vacant possession of 57-76 Northchurch) it be resolved to appropriate the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972 (as amended).
7. That it be confirmed that, following completion of the appropriation at paragraph 6 above, the area of council-owned land hatched black on the plan at Appendix 2 of the report identified as 57-76 Northchurch and Taplow ramp site area will no longer be required for planning purposes and it be resolved to appropriate the land to housing purposes in accordance with section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972 (as amended).
Report author: Eleanor Kelly
Publication date: 09/12/2020
Date of decision: 08/12/2020
Decided at meeting: 08/12/2020 - Cabinet
Effective from: 17/12/2020