Decision Maker: Cabinet
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: Yes
To approve the procurement strategy
RESOLVED:
That the procurement strategy outlined in the report for two separate contracts be approved:
Works Contract
· Southwark Highways Works Contracts in two lots commencing 1 July 2020 for an initial duration of five years and nine months, with an option for the council to extend for up to two further years.
o Lot A – Maintenance (for small scale reactive repairs) at an estimated maximum total cost of £15.9m (1 supplier)
o Lot B – Projects (for planned renewal / improvement projects) at an estimated maximum total cost of £55.4m (1 supplier).
Services Contract
· Southwark Highways Professional Services Contract consisting of three lots, commencing 1 January 2021 for an initial duration of five years and three months, with an option for the council to extend for up to two further years.
o Lot A - Structures Inspections and Design at an estimated maximum total cost of £7.3m
o Lot B - Highway Design and Management at an estimated maximum total cost of £11.6m
o Lot C - Drainage and SUDS (Sustainable Drainage System) Design and Management at an estimated maximum total cost of £3.6m.
Report author: Deborah Collins
Publication date: 12/12/2018
Date of decision: 11/12/2018
Decided at meeting: 11/12/2018 - Cabinet
Effective from: 20/12/2018