Gateway 1: Procurement Strategy Approval - Lift Maintenance Contract

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Procurement strategy approval

Decisions:

RESOLVED:

 

That the revised procurement strategy outlined in the report for the lift maintenance contracts, contract A, north of the borough at an estimated annual cost of £1,721,000 and contract B, south of the borough at an estimated annual cost of £1,398,000 for a period of five (5) years from 8 September 2014, with the potential for two (2) twelve month extensions, subject to performance, making an estimated contract value of £21,833,000 be approved.

Report author: Gerri Scott

Publication date: 01/07/2013

Date of decision: 26/06/2013

Decided at meeting: 26/06/2013 - Cabinet

Effective from: 05/07/2013