Decision details

Approval of the Council's Transport for London funded work programme for 2013/14 and indicative programme to 2014/15 for submission to Transport for London

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve details of the annual LIP submission to TfL for 2013/14 schemes in accordance with the Transport Plan

Decisions:

RESOLVED:

 

Decisions of the Cabinet

 

1.  That the content of the council’s proposed submission to Transport for London (TfL) identifying transport projects to be delivered with TfL Local Implementation Plan (Lip) funding in 2013/14 and the indicative programme of work for 2014/15, as contained in Appendix A of the report be agreed.

 

2.  That the identified programme be submitted to Transport for London by 5 October 2012.

 

3.  That the agreed programme as set out in Appendix A of the report be implemented.

 

Decisions of the Leader of the Council

 

4.  That authority be delegated to the cabinet member for transport, environment and recycling to amend the programme for 2013/14 should any variations to the proposed programme be required. The cabinet member shall consult community council chairs regarding scheme changes in their area.

 

5.  That authority be delegated to the cabinet member for transport, environment and recycling to determine the most appropriate use of the £100k discretionary funding allocated by Transport for London for 2013/14.

Report author: Eleanor Kelly

Publication date: 27/09/2012

Date of decision: 25/09/2012

Decided at meeting: 25/09/2012 - Cabinet

Effective from: 04/10/2012