21/05/2020 - Gateway 1 - Contractor Services for the Tissington Court New Homes Delivery Project ref: 7100    Recommendations Approved (subject to call-in)

Decision Maker: Cabinet Member for Social Regeneration, Great Estates and New Council Homes

Decision published: 22/05/2020

Effective from: 02/06/2020

Decision:

1.  That the procurement strategy for new build works at the Tissington Court (as further detailed in the Background Information section of this Gateway Approval report) at an estimated cost of £11,500,000 be approved. It is estimated that the contract will be 18 to 24 months.

 

2.  That the delegation of the Gateway 2 award decision to the Strategic Director of Housing and Modernisation, in consultation with the Cabinet Member for Social Regeneration, Great Estates and New Council Homes be approved, for the reason outlined in paragraph 33 of the report.

 

Wards affected: Rotherhithe;

Lead officer: Michael Scorer


21/05/2020 - Covid-19 - Post lockdown highway schemes

To approve a number of highway schemes across the borough that will assist social distancing and promote cycle and pedestrian safety.

Decision Maker: Cabinet Member for Environment, Transport and the Climate Emergency

Decision due date: Not before 01/06/2020

Wards affected: (All Wards);

Lead officer: Dale Foden

Notice of decision: 21/05/2020


21/05/2020 - Gateway 1 - Procurement Strategy Approval Contractor Services for the Lindley Estate New Homes Delivery Project ref: 7099    Recommendations Approved (subject to call-in)

To approve the procurement strategy for new build works at the Lindley Estate and the delegation of the Gateway 2 award decision to the strategic director of housing and modernisation, in consultation with the cabinet member for social regeneration, great estates and new council homes.

Decision Maker: Cabinet Member for Social Regeneration, Great Estates and New Council Homes

Decision published: 21/05/2020

Effective from: 30/05/2020

Decision:

1.  That the procurement strategy for new build works at the Lindley Estate (as further detailed in the Background Information section of this Gateway Approval report) at an estimated cost of £13,000,000 be approved. It is estimated that the contract will be 18 to 24 months.

 

2.  That the delegation of the Gateway 2 award decision to the strategic director of housing and modernisation, in consultation with the cabinet member for social regeneration, great estates and new council homes, for the reason outlined in paragraph 33 of the report, be approved.

Wards affected: Old Kent Road;

Lead officer: Michael Scorer


20/05/2020 - Council Tax Discretionary Relief Policy - inclusion of COVID-19 relief classes ref: 7098    Recommendations Approved

To extend the Council Tax Discretionary Relief Policy

Decision Maker: Cabinet Member for Finance, Performance and Brexit

Decision published: 20/05/2020

Effective from: 20/05/2020

Decision:

 

1.  That the extension to the Council Tax Discretionary Relief Policy at Appendix 1 of the report be agreed.

 

2.  It be agreed that a minimum of £2m of the COVID-19 hardship fund budget from Government be utilised to finance the one-year extension.

 

3.  It be agreed that the strategic director of finance and governance be provided with the delegated responsibility to make future decisions on amendments to the extended policy following further review and consultation.

Wards affected: (All Wards);

Lead officer: Dominic Cain


20/05/2020 - Charter for influencing and benefiting from new council homes development (Charter of Principles)

To approve the amended wording to the Charter for influencing and benefiting from new council homes development (Charter of Principles), and the interim modifications to the council’s engagement process whilst government restrictions on social distancing are applied.

 

Decision Maker: Cabinet Member for Social Regeneration, Great Estates and New Council Homes

Decision due date: Not before 27/05/2020

Wards affected: (All Wards);

Lead officer: Stuart Davis

Notice of decision: 20/05/2020


19/05/2020 - Wood Vale Highway Improvements

To approve the proposed highway improvements.

Decision Maker: Cabinet Member for Environment, Transport and the Climate Emergency

Decision due date: Not before 26/05/2020

Wards affected: Dulwich Hill; Dulwich Wood;

Lead officer: Dale Foden

Notice of decision: 19/05/2020


19/05/2020 - Gateway 3 – Variation Decision Inclusion of Hard FM Services into the Interserve Facilities Management Contract

Decision Maker: Strategic Director of Housing and Modernisation

Decision due date: Before 29/05/2020

Wards affected: (All Wards);

Lead officer: Paul Symington

Notice of decision: 19/05/2020


18/05/2020 - GW2 - Approval of the procurement of contractor services Sedgmoor Place ref: 7097    Recommendations Approved (subject to call-in)

Contract award approval

Decision Maker: Strategic Director of Housing and Modernisation

Decision published: 18/05/2020

Effective from: 27/05/2020

Decision:

1.  That the award of a works contract for 13 new homes at Sedgmoor Place SE5 to Neilcott Construction Limited for a period of 65 weeks including mobilisation be approved.

 

2.  That it be noted the total scheme cost includes associated on-costs and a 5% contingency sum.

Wards affected: St Giles;

Lead officer: Michael Scorer


12/05/2020 - Gateway 1 - Contractor Services for the Rennie Estate New Homes Delivery Project

Procurement Strategy Approval

Decision Maker: Cabinet Member for Social Regeneration, Great Estates and New Council Homes

Decision due date: 05/2020

Wards affected: South Bermondsey;

Lead officer: Michael Scorer

Notice of decision: 01/04/2020


14/04/2020 - Home Owner Fund Budget and Reserve Proposal 2019 - 2020 ref: 7096    Recommendations Approved

To approve the proposed 2019-20 Home Owners Fund.

.

Decision Maker: Cabinet Member for Housing Management and Modernisation

Decision published: 12/05/2020

Effective from: 20/05/2020

Decision:

1.  That the proposed 2019-20 Home Owners Fund (HOF) budget of £375,133 as summarisedin Appendix 1 of the report be approved, following consultation with the Home Owner Fund Management Committee (HFMC) and the Home Owner Council (HOC).

 

2.  That it be noted that – at the request of the previous cabinet member – the budget proposed for this year also includes proposals for expenditure of HOF reserves, meaning that expenditure exceeds revenue income, with the gap being filled by HOF reserves.

 

3.  That it be noted that this approval is further subject to the requirement that expenditure involving the procurement of external services is subject to compliance with current internal governance requirements and procurement and financial practices as set out in paragraph 22 and in Appendix 2 of the report.

 

Wards affected: (All Wards);

Lead officer: Michael Scorer


11/05/2020 - Gateway 3 - Variation Decision Professional Technical Services Contract ref: 7095    Recommendations Approved

Contract variation (extension)

Decision Maker: Cabinet Member for Housing Management and Modernisation

Decision published: 11/05/2020

Effective from: 19/05/2020

Decision:

1.  That the variation of the first Professional Technical Services contract to Calfordseaden LLP to extend the term of the contract for a period of 12 months from 1 May 2020 (as further detailed in paragraph 15) at an estimated additional cost of £2m making a revised estimated contract value of £10.6m for seven years and six months be approved.

 

  1. That the variation of the second Professional Technical Services contract to Potter Raper Ltd (formerly Potter Raper Partnership) to extend the term of the contract for a period of 12 months from 1 May 2020 (as further detailed in paragraph 15) at an estimated additional cost of £1m making a revised estimated contract value of £8.35m for seven years and six months be approved.

Wards affected: (All Wards);

Lead officer: Michael Scorer