Gateway 2 - Contract Award Construction of new build units at Pelier Street

03/04/2018 - Gateway 2 - Contract Award Construction of new build units at Pelier Street

1.  That the award of the works contract for Pelier Street to Neilcott Construction Ltd for the sum of £4,831,910, commencing Monday 2  April 2018 for a period of 56 weeks from site possession be approved.

 

2.  That the total scheme costs of £5,699,713 as detailed in paragraph 60 of the report be noted.