Minutes:
An officer introduced the report. The committee considered the information in the report.
RESOLVED:
1. That the release of £5,212,735.34 from the Section 106 funding set out below be authorised.
Project |
Number of Agreements |
Appendix |
Total S106 Funding |
Elephant and Castle |
44 |
1 |
£3,521,153.22 |
Traffic Order Regulations |
1358 |
2 |
£505,915.48 |
CPZ |
17 |
3 |
£197,313.15 |
TOTAL |
260 |
|
£4,224,381.85 |
2. That in addition to the above sums, the release of £988,353.49 of interest, associated with 64 separate agreements be approved.