Decision Maker: Cabinet Member for Housing
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To approve the procurement strategy.
1. That the procurement strategy for new build works at Fendall Street and Maltby Street (as further detailed in the Background Information section of this Gateway Approval report) at an estimated cost of £14,050,000 with an estimated contract duration of 18 to 24 months be approved.
2. That the delegation of the Gateway 2 award decision to the Strategic Director of Housing and Modernisation, in consultation with the cabinet Member for Social Regeneration, Great Estates and New Council Homes, for the reason outlined in paragraph 39 below be approved.
Publication date: 15/10/2020
Date of decision: 15/10/2020