Decision details

Hampton and Steedman Streets Improvements

Decision Maker: Cabinet Member for Environment, Transport Management and Air Quality

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

 

1.  Approves the implementation of the highway improvement scheme at Hampton Street and Steedman Street, Newington and North Walworth Wards as per the drawing in Appendix A subject to detail design, road safety audit and the outcome of the necessary statutory consultation.

 

2.  Acknowledges the desire from consultees to allow contraflow cycling on the eastern half of Hampton Street and approves the additional implementation of that facility as part of the project, subject to design, road safety audit, budget and the outcome of the necessary statutory procedures.

 

3.  Acknowledge the desire from a local business to alter the proposed parking layout on Steedman Street, under the railway bridge, and approves the additional implementation of two new shared use bays in place of the existing permit holders bays as part of the project, subject to the outcome of the necessary statutory procedures.

Decision:

1.  That the implementation of the highway improvement scheme at Hampton Street and Steedman Street, Newington and North Walworth Wards as per the drawing in Appendix A subject to detail design, road safety audit and the outcome of the necessary statutory consultation be approved.

 

2.  That that the desire from consultees to allow contraflow cycling on the eastern half of Hampton Street be acknowledged and that the additional implementation of that facility  as part of the project, subject to design, road safety audit, budget and the outcome of the necessary statutory procedures be approved.

 

3.  That the desire from a local business to alter the proposed parking layout on Steedman Street, under the railway bridge be acknowledged and that the additional implementation of two new shared use bays in place of the existing permit holders bays as part of the project, subject to the outcome of the necessary statutory procedures be approved.

Publication date: 11/07/2018

Date of decision: 10/07/2018

Effective from: 19/07/2018

Accompanying Documents: