Decision details

Gateway 2 Contract Award - Rotherhithe New Road (Balman House, Oldfield Grove & St Helena Road) Refurbishment Works QHIP 16/17

Decision Maker: Strategic Director of Housing

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the contract award for quality homes investment programme (QHIP) works relating to Rotherhithe New Road (Balman House, Oldfield Grove & St Helena Road, SE16).

Decision:

That the award of the Rotherhithe New Road (Balman House, Oldfield Grove & St Helena Road) Refurb Quality Homes Investment Programme 2016/17 works via a mini-competition from the major works constructor framework to A&E Elkins Ltd for a period of 22 working weeks be approved.

Publication date: 26/06/2017

Date of decision: 22/06/2017

Effective from: 04/07/2017